06/05/2010
Abbey Mills, West Ham
Project Status
Current Project
Project Outline
West Ham Flood Alleviation Scheme
Description
Electrical and Instrumentation services for a new Sewage Pumping Station at Abbey Mills, West Ham.
Full Description
As part of a scheme to stop more than 800 West Ham homes flooding with sewage.
overall three-year project, one of the largest sewer flooding schemes Thames Water has ever carried out, includes:
A new, two-mile sewer, 2.8 metres wide - one of the largest sewers built in London - to carry away excess rainwater and sewage during storms, preventing flows backing up into streets and properties;
A new sewage pumping station at Abbey Mills in Stratford, east London;
3.5 miles of new and larger sewers linking to the main sewer tunnel.
Contract Duration
8 weeks
Contract Value
£160k
Additional Contract Details
Services Provided
Electrical & Instrumentation
Main Contractor
Costain
End User
Thames Water
Consultants
MWH
Completion Date
01/07/2010
Division
Process
West Ham